DT and Optimization Engineer

Gender: Male
Nationality: Cambodian

Work Experience

DT and Optimization Engineer

- February 2016 to Present

CCPL (Cambodia) Co., LTD - phnom penh

  • Investigates Call Drop and network failure 
  • Consolidates and solves all issue and complaint of network performance 
  • Monitors and maintains all testing equipments 
  • Perform other duties as assigned by management 


Site Engineer

- August 2014 to February 2016

ZTE HK (Cambodia) Co., LTD - phnom penh

  • Site acquisition and TSSR survey report 
  • Site engineering installation procedure and Site Audit (BTS, MW, DWDM, Power) & Site Documentations  
  • Supervisor subcontractor to new TI installation Support and Maintenance subcontractor to fix troubleshooting issue 
  • Project coordinator for DWDM/FDD-LTE Core Network installation and integration  
  • Subcontractor control, manager and control 4 subcontractors to install new BTS, MW, DWDM and PTN6110  
  • Create/ Manage Hardware installation Guide and Commissioning Guide 
  • Onsite SDR B8700 commissioning and fix troubleshooting PTN6120 
  • Data/Re- Configuration and Software activated element as PLAT, UMTS, LTE and GSM file 
  • Configuration Fiber Optical and Commissioning 
  • Pre-PAT testing and Site Auditor with Quality Control standard 
  • Pre-installation and Installation SDR B8700, PTN 6110 and DWDM 
  • Supervisor Subcontractor to Swap & Dismantle Existing Materials Support and Maintenance subcontractor to fix troubleshooting issue 
  • BTS and PTN commissioning, PAC and apply FAC 
  • BTS integration (GSM & UMTS & LTE) 
  • DWDM Testing Fiber cable, Splicing test, Power budgeting and Commissioning 
  • Onsite Inspection and Site Audit, Resolve and fix troubleshooting complain from customer and kept off meeting with customer owner 
  • Check and verify implementation activated and On air  
  • Telnet and loop test NE-IP is normal and status 
  • Check and Modify NE data Configuration status and alarm on site 
  • Provide training new technical to subcontractor 
  • GSM/UMTS/LTE Project rollout - 2G Swap, 3G/4G new network integration 


Assistant Project Manager

- May 2012 to July 2014

Chum Corporation & Engineering Service Co., LTD - phnom penh

  • Pre-sale: support information of equipment manufacturing to meet customer’s requirements based on contract and prepare the contract with customer and prepare Responsibility matrix and confirm with customer 
  • Implementation: scheduling project roll-out plan, review cutover plan, subcontractor management, quality control, budget planning, resource planning 
  • Project Kick-off Meeting: subcontractor scope of work (SOW) Preparation subcontractor resource analysis base on implementation period and internal training course. 
  • Interface with Customer: support and solve all the problem with customer complain and support for technical problem with customer 
  • Survey: Manage and Review template the TSSR for subcontractor during site survey and SSV report 
  • Documentation control: TSSR report(Survey template , PAT Document , QC report , packing list , return note , delivery note, Transfer Note, site survey report, PAC and FAC 
  • Internal management: control manpower warehouse, Material team, safety and delivery team, setup planning to all of them according to implementation plan 
  • Subcontractor control: manage and control subcontractors to delivery and safety installation with implementation plan on time 
  • Customer suppliers follow up: Gen-Set ,BTS,BSC,MW,SDH and network power system. 


Assistant Project Manager

- December 2010 to May 2012

Power-Telco (Cambodia) Co., LTD - phnom penh

  • Manage and submitted PAC, FAC  
  • Coordinator all subcontractor to solved troubleshoot issues 
  • Manage and Created QC (Quality Checklist) 
  • Project coordinator for GSM/UMTS/LTE Core Network installation and integration  
  • Created TSSR template for subcontractor to do Pre-install and install 
  • Check and verify MR(Material request ),DN(Delivery Note),RN(Return Note) 
  • Created Plan, Schedule and Pre-PAT template for subcontractor to do PAT and testing Issue requiring. 
  • Do /follow up subcontractor daily report, weekly report, and monthly report for directly to project Manager required. 
  • Directly on site support and fix troubleshooting  
  • Assisted PM to train subcontractor for Project Procedure , guideline and Planning 
  • Assisted PM to progress report to customer required by management 
  • Do summary progress report and troubleshooting 
  • Do technical site survey report and Do report TSSR, SSV 
  • Supervisor team installation to swap and dismantle existing materials 
  • Pre-PAT and Pre-Commissioning BTS3900,APM30H, DBS3900 
  • MW Alignment (Optix RTN910, RTN950) 



Education

BA in Computer Science and Engineering

- 2005 to 2009

Royal University of Phnom Penh - Cambodia


Skill

COMPUTER SKILLS: Microsoft Office, Internet, E-mail, AutoCAD 2D, coral draw, MS Visio, MS Project, Minind management

Language

English (Fluent) , Chinese (Mandarin) (Basic) , Khmer (Native)
Last updated: 5 years ago
Download: 1
View: 2710
ID: 70

Resumes you may be interested in

DT and Optimization Engineer

CCPL (Cambodia) Co., LTD

Cambodian

Work Experience

DT and Optimization Engineer

CCPL (Cambodia) Co., LTD - phnom penh

February 2016 to Present

Site Engineer

ZTE HK (Cambodia) Co., LTD - phnom penh

August 2014 to February 2016

Assistant Project Manager

Chum Corporation & Engineering Service Co., LTD - phnom penh

May 2012 to July 2014

Assistant Project Manager

Power-Telco (Cambodia) Co., LTD - phnom penh

December 2010 to May 2012

Education

BA in Computer Science and Engineering

Royal University of Phnom Penh - Cambodia

2005 to 2009

Skill

COMPUTER SKILLS: Microsoft Office, Internet, E-mail, AutoCAD 2D, coral draw, MS Visio, MS Project, Minind management

Language

254 (238) , 260 (240) , 236 (237)

Resumes you may be interested in